Air conditioning in clean rooms and pharmaceutical laboratories (III)

Third and final part of this special. This time we will delve into the topic of forgotten design criteria in HVAC projects.

by Eng. María Lucía Botero N*

HVAC design processes often become mechanical: CT C, technology selection, equipment selection, duct design, piping, control and budget.
But sometimes what can cause the failure of the project? When I say failure I mean that a computer operates incorrectly, that the conditions are not achieved, that control fails, that the client does not maintain the equipment properly, etc.

Well, here I am going to present a summary of some of those points that are left forgotten in the day to day of design, all to leave one project and move on to the next as quickly as possible.
The project must be born with the understanding of its raison d'être and believe me, it is not always just about air conditioning an area, it is not so, there are many underlying reasons: the stability of a product, the operation and useful life of an electronic equipment, the success of a pharmaceutical, medical procedure; the preservation of a life using air conditioning in hospitals in critical areas and drug production. It seems logical, but in my concept it often fails from this first step: that of conceptualizing why the project was born.

The process of calculating thermal load continues. Yes, there are excellent calculation software, there are regulations that are clear guides for a design, almost one could say that they are the navigation chart and if some variations are not made, nothing will happen. There is also LEED certification, which gives the project a class of maximum energy saving. But what if we use all these valuable tools and do not stop to review small details that repeatedly cause projects to fail.

Now then I will mention some of these details:
1. What is the simultaneity of use of the system? By this I mean how the operation will be given, whether to partial loads and / or total loads or failing that both. This is often one of the most difficult problems to attack, because once the equipment is purchased there is no going back. And it is that the decision of the size of the system is made because it becomes common to repeat which is the most efficient system in "tables of selections", but what is the operation in real life? Did you analyze if it is useful for your client to have on paper the most efficient equipment in history, but it turns out that it was not operating at its best point of efficiency?

2. Technology selection: Although this point is highly linked to the previous one, they complement each other widely. Well, what happens here: it is necessary to make an analysis of a number of questions that we must ask ourselves, after determining the thermal load and simultaneity, where particularly many of the answers will be delivered from different areas of the client, then some of them: Does the client already have a technology installed? How has your experience been? Are you happy with the current provider or want to switch? What process do you have of maintenance, spare parts or contingency in case of failure? What budget does the project have?

And something that seems basic, but it is not, is to question the location or the ease of monitoring the project and linking it to know if it will have a stand alone control system or with the possibility of remote monitoring. Well, with those questions and many others, many failures can be avoided in the future. Examples:

A. Choose a variable refrigerant system and not have the trained personnel and / or response of the supplier.

B. Choose cold water systems condensed by water, because they are more efficient and the client does not know, nor does he have the slightest idea of keeping the tower water circuit in optimal conditions, which makes it useless to be in numbers a more efficient system because in the operation it will be the opposite.

C. Consider that the entire project should have the same technology, when there are areas that work at different times than the central system and redundancy was not thought of.

3. Location of equipment: this is not an easy task because it is often the struggle with architectural design, but it is there where we must be smart and achieve a negotiation with the client so that tomorrow the refrigeration technicians do not hate the consultants. How is it possible that we leave installed equipment where not even a 5-year-old child accesses? And the implications are not only maintenance, but the possibility of inspection and incorrect operation. But there are other proposals that worry me even more and are cases such as, for example, seeing a discharge to the outside of a room works in negative pressure next to a handling unit for a clean area of maximum classification.

One would think that it does not have to come in any norm because it should only be taken into account by common sense. An example for the hospital sector would be a discharge from a room of insulated next to the outside air intake of an operating room. That is why I return to the same point: there can be standards of all kinds and projects end up with your plate at the entrance of your certification process; but if this happens in the technical rooms where 95% or more have no idea that this is happening, nothing will be achieved.

4. Control system: It is a fact that already today the percentage of projects are accompanied by a control system even if it is basic, but sometimes I wonder if it is worth all that investment. Are these systems used 100% and maintained over time? For me the answer is no. You can make stunning control diagrams and sequences with great detail, but in many cases, running with luck, they work at the time of the inauguration because many times they do not work there and so they stay.

My point in this item is that you must also go through a process of identifying with the client in reality about what you want to control and what you want to monitor, so that tomorrow you do not see buried investments that will simply be "puentiadas", marking an erroneous measurement, or the saddest, with all the correct information but that absolutely nobody uses it.
Surely there will be more criteria that pass me by... the reflection for all of us consultants is to stop making the designs as if they were an online production, and spend more time analyzing, as we say, "putting ourselves on the client's shirt".

In summary, one could say that pharmaceutical laboratories, because they have in most cases defined parameters to fully comply with (temperature, HR, changes per hour, pressures, etc.); they should be supremely easy to design and there should be no flaws. However, reflection is to further study certain criteria that can be fundamental to the success of the project and are often left forgotten.

* María Lucía Botero N, is an engineer at Camilo Botero Ingenieros Asociados, you can write to the email: [email protected]

Duván Chaverra Agudelo
Duván Chaverra AgudeloEmail: [email protected]
Jefe Editorial de las revistas AVI Latinoamérica, ACR Latinoamérica, Ventas de Seguridad, Zona de Pinturas, Aftermarket Internation, Gerencia de Edificios, TV y Video, y Director Académico en Latin Press, Inc,.
Comunicador Social y Periodista con experiencia de más de 18 años en medios de comunicación. Apasionado por la tecnología y por esta industria.

No comments

• If you're already registered, please log in first. Your email will not be published.

Leave your comment

In reply to Some User
Finalists of the CALA AWARDS will travel as guests to RefriAméricas Santo Domingo

Finalists of the CALA AWARDS will travel as guests to RefriAméricas Santo Domingo

Latin America. Applications for the prestigious CALA AWARDS 2025 will be open until May 10. This award, organized by ACR Latin America, is a unique opportunity to highlight the best air conditioning...

Copeland to Showcase Innovative Cold Chain Solutions at Global Cherry Summit 2025

Copeland to Showcase Innovative Cold Chain Solutions at Global Cherry Summit 2025

Chile. Copeland, a global provider of sustainable climate solutions, will participate in the Global Cherry Summit 2025, which will be held on April 22 at the Monticello Conference Center, in San...

Carrier Receives Double Recognition at the 2025 Environment + Energy Leader Awards

Carrier Receives Double Recognition at the 2025 Environment + Energy Leader Awards

United States. The company was awarded in the Energy Innovation and Software Implementation categories for its Abound solutions, which optimize energy consumption in more than 2,500 stores in the...

Data Centers Rely on Liquid Cooling to Meet AI Energy Demand

Data Centers Rely on Liquid Cooling to Meet AI Energy Demand

Mexico. With the rise of artificial intelligence (AI), machine learning (ML), and high-performance computing (HPC), the global technology infrastructure faces a new challenge: dissipating the heat...

Chilean supermarket leads transition to sustainable A2L refrigerants with state-of-the-art technology

Chilean supermarket leads transition to sustainable A2L refrigerants with state-of-the-art technology

Chile. A well-known supermarket chain in the south-central part of the country became a pioneer by implementing refrigeration systems based on new generation A2L refrigerants, which offer a...

Mergers and acquisitions in the HVAC equipment sector grow driven by technology demand

Mergers and acquisitions in the HVAC equipment sector grow driven by technology demand

International. The HVAC market has seen remarkable growth, driving an increase in mergers, acquisitions (M&A), and investments in key technologies.

New corrosion protection in SISTEVEN fans

New corrosion protection in SISTEVEN fans

International. The company has begun to incorporate Magnelis-coated sheet steel into the production of its fans and ventilation systems.

Smart refrigeration gains ground in the food industry

Smart refrigeration gains ground in the food industry

International. Danfoss and Microsoft announced the expansion of their strategic collaboration, established in 2019, with the aim of accelerating the development and implementation of solutions based...

LG Launches Free Online Academy to Train HVAC Professionals

LG Launches Free Online Academy to Train HVAC Professionals

International. LG has launched a new free digital platform for the training of HVAC consultants and installers, registration is officially open. 

ACAIRE will hold a union meeting in Medellín to present the 2025 agenda and news of the RETSIT

ACAIRE will hold a union meeting in Medellín to present the 2025 agenda and news of the RETSIT

Colombia. Next Wednesday, April 23, 2025, the HVAC&R sector has a key appointment in Medellín with the Trade Union Meeting organized by ACAIRE, a free event that will bring together...

Free Subscription
Remember Me
SUBSCRIBE TO OUR NEWSLETTER
DO YOU NEED A SERVICE OR PRODUCT QUOTE?
LASTEST INTERVIEWS
SITE SPONSORS










LASTEST NEWSLETTER
Ultimo Info-Boletin